The Subcontract includes the construction of civil & building works for a 2400 MW power plant
Photo Gallery
The Subcontract includes the construction of civil & building works for a 2400 MW power plant
a) Civil Works for Power Block# 3 & # 4 Area:
Foundation & Structures, Cable Routing Work (Cable Trench, Duck bank, Electrical Manhole, etc.) Pipe laying Work (Civil works for pressured-pipe laying, Pipe sleeper, Direct buried, Thrust block, pipe trench/ tunnel) and Drainage (Storm water & sanitary pipes).
b) Civil Work for BOP Area:
Foundation & Structures, Cable Routing Work (Cable Trench, Duck bank, Electrical Manhole, etc.) Pipe laying Work (Civil works for pressured-pipe laying, Pipe sleeper, Direct buried, Thrust block, pipe trench/ tunnel), Drainage (Storm water & sanitary pipes) and Fence & gate work (BOP+ Tank Form).
c) Civil Work for Cooling Water Pipeline:
Pipe laying Work (Civil works for pressured-pipe laying, pipe sleeper, Direct buried, Thrust block, pipe trench/tunnel).
d) Building Works for Power Block# 3 & # 4 +BOP:
Temporary work, Earthwork, Reinforced concrete work, Masonry work, Plaster work, Painting work, Waterproofing work, Tile and flooring work, Interior work, Door and window work, Miscellaneous metal work (for RC building), Miscellaneous work, and steel Structure work (Erection).
Total floor area of 107,367 Sq.m buildings