The project includes Construction of Railway track for Cargo trains and Connection of 2nd Container Terminal Inside King Abdul Aziz Port in Dammam with the Existing Railway
Photo Gallery
The project includes Construction of Railway track for Cargo trains and Connection of 2nd Container Terminal Inside King Abdul Aziz Port in Dammam with the Existing Railway
- Dismantling of existing track of length 1,131 m and stacking the dismantled material in the storage areas designated by the Engineer. Also included the leveling of the final surface after spraying of water, rolling and compaction.
- Demolition of one existing turnout and handing over of dismantled material to SRO stores.
- Construction of 8,173 m of railway track include; construction of embankment and preparation of formation surface (for 8,173 m)
- Supply and spreading of ballast for the 8,173 m railway track.
- Supply and installation of concrete sleepers with Vossloh fastenings
- First leveling and Second general leveling for the 8,173 m track
- Destressing of track (8,173 m)
- Supply, driving, laying, ballasting, tamping, of 17 nos. new turnouts
- Construction of 6 nos. asphalt crossing with concrete sleepers, Vossloh fastening and associated works